Construction work on the new CLT and glulam timber gym in Cremona is progressing rapidly.
Following the definitive and executive structural design phase, we have finally moved on to the operational structural supervision phase.
In recent months, acting as structural works supervisors, we managed the construction of the foundations and subsequently the timber elevation structures.
After arranging the installation of the glulam wood columns, we supervised the installation phases of the lattice beams with a span of approximately 25 m.



The secondary glulam wood framing is braced with a 6 cm thick CLT wood panel.
The changing rooms are located adjacent to the gymnasium and are constructed in CLT wood for both the walls and the roof slab completion.
Assignment: Detailed structural design – construction structural design – operational structural supervision.