Category: Structural Timber Design

Projects where structural timber design is especially showcased, or simply projects we are proud of and that represent us.

  • New CLT wood gym in Cremona: work in progress

    New CLT wood gym in Cremona: work in progress

    Construction work on the new CLT and glulam timber gym in Cremona is progressing rapidly.

    Following the definitive and executive structural design phase, we have finally moved on to the operational structural supervision phase.

    In recent months, acting as structural works supervisors, we managed the construction of the foundations and subsequently the timber elevation structures.

    After arranging the installation of the glulam wood columns, we supervised the installation phases of the lattice beams with a span of approximately 25 m.

    The secondary glulam wood framing is braced with a 6 cm thick CLT wood panel.

    The changing rooms are located adjacent to the gymnasium and are constructed in CLT wood for both the walls and the roof slab completion.

    Assignment: Detailed structural design – construction structural design – operational structural supervision.

  • New CLT Wood School in Grezzana – Verona: Work in Progress

    New CLT Wood School in Grezzana – Verona: Work in Progress

    Construction work on the new CLT wood school in Grezzana, province of Verona, is proceeding swiftly.

    In recent months, as structural works supervision, we have handled various preparatory activities for the construction of the new wood school.

    We began with the strip-out phases of the existing building and its demolition.

    During demolition, an unforeseen situation emerged at the existing foundation level, which led us to redesign the foundation structures.

    Before proceeding with the excavation of the area, two micropile “Berlin walls” were constructed.

    One was built near the existing school building and is of the anchored type.

    The other, directly at the boundary, was designed with an inclined diagonal bracing, as it was not possible to use anchors in the ground.

    The excavation phases then continued down to the design level.

    The backfilling phases, carried out in steps, were followed with great care to carefully assess the compaction state of the soils together with the necessary plate load tests.

    The foundation blinding concrete was then poured, followed by the raft foundations and the subsequent void former system with overlying concrete slab.

    We are now ready to supervise the installation work of the building’s CLT wood structures.

    Assignment: Final structural design – detailed structural design – structural works supervision

  • Innovation Hub, Faculty of Engineering, Padua: work in progress

    Innovation Hub, Faculty of Engineering, Padua: work in progress

    Construction work on the new Innovation Hub – Faculty of Engineering of Padua is proceeding swiftly.

    We began our structural works supervision assignment at the beginning of February.

    The first month was dedicated to completing the foundation works: an 80cm thick slab covering approximately 2,000 square meters. The pouring operations were carried out in 2 phases, one of which involved 1,400 cubic meters.

    The installation of the timber structures began in March, following several days spent preparing the steel curbs required for positioning the walls above.

    Wall installation proceeded very swiftly, as did the installation of the first floor structures.

    Four weeks have passed since the start of the timber structure installation; one team is already beginning to install the second-floor beams while another team completes the first floor.

    Just to give an idea of the installation speed of the system and the building’s dimensions:

    1 month = 900 cubic meters of timber structures installed!

  • Contract Awarded: We Will Design the Timber Structures for the New Rachetti Classical High School

    Contract Awarded: We Will Design the Timber Structures for the New Rachetti Classical High School

    Fornale Engineering has been awarded the contract for the detailed and executive structural design of the new Rachetti Classical High School in Cremona.

    The complex comprises 4 main volumes of 2 floors each, with a total floor area of approximately 9,200 m².

    In addition to spaces dedicated to teaching and laboratories, a gymnasium of approximately 700 m² is included within the volumes.

    The foundation structures will be of the raft type, from which the first and second floor elevations in CLT panels will rise.

    The floors are designed with a system of glulam beams and CLT slabs.

    We estimate a total use of approximately 2,400 m³ of CLT and 650 m³ of glulam.

    We are proud to have been awarded the contract and to be working on the design of this important project in a temporary joint venture with our colleagues at Holzner&Bertagnolli.

    This represents a major challenge for us and for the public administration that has committed to the realization of this project using timber structures.

    A concrete commitment that moves in the precise direction of reducing CO2 emissions associated with the use and production of construction materials.

    The use of load-bearing timber structures will result in a reduction in CO2 emissions that we estimate to be approximately 3,000 tons of CO2.

  • Studiofornale.it wins the design contract for the new Faculty of Engineering – Innovation Hub in Padua!

    Studiofornale.it wins the design contract for the new Faculty of Engineering – Innovation Hub in Padua!

    Fornale Engineering has been awarded, in a temporary partnership with Settanta7 and Stain srl, the contract for the design of the new Faculty of Engineering-Innovation Hub in Padua.

    Fornale Engineering will handle the structural design of the entire building.

    It will be a 4-story building of approximately 2,000 sqm per floor that will accommodate 3,000 students.

    Except for the reinforced concrete foundation slab, the entire building will be designed with load-bearing timber structures, making extensive use of glulam for beams and columns and CLT for shear walls and floors.

    The bracing walls will be constructed with CLT panels of variable thickness on each floor for a total height of 19.5 m.

    The floors, spanning nearly 12 meters, will be designed as CLT-glulam-CLT box-type systems to reduce the structural thickness of the floors.

    The facade system will be prefabricated timber with a non-load-bearing frame structure.

    The total project cost is estimated at approximately €18.5M.

    It will be a great challenge! Stay tuned.

    We are always looking for new challenges..if you have projects requiring strong expertise in the world of timber structures, contact us!!

  • CLT wood church in Casalnuovo di Napoli

    CLT wood church in Casalnuovo di Napoli

    The project for the new CLT wood church for the community of Casalnuovo di Napoli was awarded 2nd Prize.

    A very interesting project that involved us as structural consultants for the Eusebi&Partners architecture firm.

    PROJECT SUMMARY

    The design concept involved the creation of two square-based volumes measuring 22x22x22 m connected by a tunnel; one used as a church and the other for the parish’s multi-purpose activities.

    A hyperbolic paraboloid roof slab was planned for the church volume, while a flat slab was designed for the community services volume.

    CLT LOAD-BEARING STRUCTURES

    The design team immediately opted for the use of timber structures, leading to our involvement as expert consultants for timber buildings.

    TIMBER CHURCH STRUCTURES

    We designed “box” walls with a maximum height of 22 m, composed of glulam columns working in conjunction with CLT panels on both sides.

    The roof slab is highly complex, featuring a hyperbolic paraboloid shape.

    A very dense structural grid was planned, consisting of compressed concave glulam arches and sections of convex glulam beams in tension.

    The structural grid was optimized to limit thrust and tension on the heads of the columns that form the facades, which reach 22 m in height.

    FUNCTIONAL SPACE STRUCTURES

    The load-bearing structures for the area dedicated to public community spaces are much more regular and simple.

    CLT walls were planned for the ground floor, continuing up to the roof, while a large portico area is supported by glulam columns.

    The flat slabs were designed using CLT.

    PROFESSIONAL ASSIGNMENT

    • Preliminary structural design for the CLT wood church walls and glulam hyperbolic slab

    For detailed technical information on the project, please contact us here.

  • CLT apartment building in Brianza

    CLT apartment building in Brianza

    The three-story CLT apartment building constructed in Brianza is now ready for occupancy.

    Fornale Engineering handled the detailed engineering and production release of the project, including the creation of CAD/CAM files, cutting lists, and the necessary hardware specifications.

    PROJECT SUMMARY

    The project involves the construction of a CLT apartment building spanning three staggered levels with a footprint of approximately 450 sqm.

    The CLT wood walls rest on a perimeter concrete upstand to ensure the durability of the structure.

    The floor slabs are made of 200 mm thick CLT panels, with intermediate steel beams incorporated where necessary.

    The CLT building houses eight apartments, some with significant floor areas, spanning multiple floors with internal staircases.

    There are two stair/elevator shafts constructed using full-height CLT panels.

    The roof structures vary by apartment; some sections feature flat CLT slabs on glulam beams, while others have traditional gabled roofs made of glulam.

    During project development, we addressed the challenge of three different foundation levels, combined with the fact that many apartments spanned multiple floors, often straddling the points where the base levels changed.

    This required particular attention during the creation of the 3D model and the shop drawings.

    ASSIGNMENT
    • Detailed engineering of CLT wood structures
    • Production of CAD/CAM shop drawings
    • Production of cutting lists, panels, and hardware
    • Assembly plan

    Are you looking for an engineering firm that operates exclusively in the timber building sector? Contact us!

  • Multi-story CLT buildings in Verona

    Multi-story CLT buildings in Verona

    The construction site has been completed, where we were involved as structural designers for the construction project of 2 three-story CLT wooden buildings in Verona.

    PROJECT SUMMARY

    The project consists of the construction of 2 three-story buildings with a load-bearing CLT timber structure in Verona.

    First, the reinforced concrete basement of approximately 500 m² was constructed, designated for garages and storage rooms, divided into 2 sections corresponding to the units above.

    Above the precast slab, the two CLT buildings were constructed, each approximately 120 m² in plan.

    Both buildings were constructed in CLT by 2 different contractors. We designed and verified the structures to ensure alignment with the mechanical resistance of the products used in both cases, both for CLT and hardware. CLT panels from different suppliers were used, as well as different hardware suppliers.

    The elevation walls were constructed with CLT panels installed on concrete plinths, as were the elevator shafts.

    The floors were constructed with glued laminated timber beams and an overlying composite concrete slab.

    The stairwells were constructed entirely in CLT in one building, while in the other the client chose to use a prefabricated staircase.

    The roof floors were constructed in spruce glued laminated timber.

    In one of the two CLT buildings in Verona, a tile roofing system was used, while in the other a standing seam metal sheet was chosen.

    Given the mechanical and electrical system choices, coordination with the systems engineer during the design phase was essential to properly plan and define niches and service shafts.

    Assignment: Detailed design of CLT timber structures, detailed design of reinforced concrete

    Are you looking for an expert technical consultant in timber building design? Contact us!

  • XLAM Timber Villa in Brianza

    XLAM Timber Villa in Brianza

    The load-bearing structures of this XLAM timber villa built in Brianza have been completed.

    PROJECT SUMMARY

    The project involves the construction of an XLAM timber villa with approximately 220 square meters of floor area.

    On the upper level, there is a bedroom accessed via a mezzanine open to the living room below.

    The ground floor bedrooms and kitchen have a lowered ceiling at 2.9 m, unlike the living room where the glulam timber roof deck is visible.

    There are two main volumes with gable roofs interrupted by a tower with a flat roof.

    MATERIALS USED

    100 mm 3-layer cross-laminated timber panels were used for the construction of the load-bearing timber structures in elevation.

    The roof deck was constructed in glulam timber with overlaid planking and OSB3 bracing panel.

    Assignment: Executive design of XLAM timber structures, CAD/CAM file preparation, assembly plan

    If you are looking for experienced timber structure designers, contact us!

  • Cross-Laminated Timber Tourist Complex on Lake Garda

    Cross-Laminated Timber Tourist Complex on Lake Garda

    The project in which we were involved first as consultants and then as structural designers for the cross-laminated timber structure within a campsite on Lake Garda has been completed.

    PROJECT SUMMARY

    The project involves the construction of a two-story cross-laminated timber building with a ground floor of approximately 250 sqm and a first floor, featuring large terraces, of approximately 360 sqm.

    A total of 7+7 residential units are planned for use during the tourist season.

    The structure is entirely built in CLT with 3-layer walls 8 cm thick, while the floors are of the glulam-laid type.

    The roof slab is flat and, above the structural panel and insulation, sloped planks, waterproofing membrane, and gravel are laid to ensure rainwater drainage.

    CONSULTING DURING PROJECT DEFINITION/TECHNICAL SPECIFICATIONS PHASE

    We were contacted by the client before proceeding with the selection of the contractor to define the minimum technical specifications.

    We established the minimum requirements in terms of acoustic performance, fire resistance, and thermal properties, and prepared the corresponding performance specifications.

    All individual specification items were selected and detailed. This made it possible to obtain truly comparable cost estimates.

    We provided consulting during the analysis and verification phase of the cost estimates until the selection of the winning contractor.

    CROSS-LAMINATED TIMBER PANEL DESIGN

    We carried out the detailed design of the timber structures for the entire building.

    The walls are made of 8 cm thick cross-laminated timber and double walls were designed between the different residential units.

    The floors, given the need to optimize heights, were constructed in glulam-laid configuration.

    Assignment: Pre-design technical consulting, detailed design of cross-laminated timber structures

    Are you looking for an expert technical consultant in timber building design? Contact us!

  • CLT wood house design in Mariano Comense

    CLT wood house design in Mariano Comense

    Fornale Engineering designed the structures for a new CLT wood villa with a glulam roof in Mariano Comense.

    PROJECT SUMMARY

    The villa is single-story and features a rectangular floor plan of approximately 220 sqm.

    The roof is a gable type, except for the external eaves which are designed as flat roofs.

    CLT LOAD-BEARING STRUCTURES

    The load-bearing elevation structures are made of 100 mm thick 3-layer CLT wood panels.

    The roof structure is made of glulam and consists of a main framework of ridges, hips, and valleys supported internally by steel pillars, while along the perimeter, they are anchored to the wall plates.

    The secondary beams are fixed to the main ones using pairs of full-thread screws crossed at 45 degrees.

    The roof eaves are flat and were constructed using CLT wood panels supported by a steel frame.

    PROFESSIONAL ASSIGNMENT

    • Design of CLT wood elevation structures;
    • Design of the glulam roof;
    • CLT wood and steel workshop drawings;
    • Assembly plan

    For detailed technical information on the project, please contact us here.

  • Studiofornale.it in the ANCE national magazine: our seismic retrofitting project selected

    Studiofornale.it in the ANCE national magazine: our seismic retrofitting project selected

    An article regarding a seismic retrofitting project designed by us in the province of Modena appeared in November in the magazine “Rassegna tecnologica” No. 9 of the National Association of Building Contractors (ANCE).

    The article describes the technique used for the seismic retrofitting of the building, which was severely damaged by the 2012 earthquake.

    The article describes the intervention methods proposed and implemented on the timber floors; further interventions on the building can be found in this post.

    For those interested in learning more, the link to the full post is provided below: