Construction work on the new Innovation Hub – Faculty of Engineering of Padua is proceeding swiftly.
We began our structural works supervision assignment at the beginning of February.
The first month was dedicated to completing the foundation works: an 80cm thick slab covering approximately 2,000 square meters. The pouring operations were carried out in 2 phases, one of which involved 1,400 cubic meters.
The installation of the timber structures began in March, following several days spent preparing the steel curbs required for positioning the walls above.
Wall installation proceeded very swiftly, as did the installation of the first floor structures.
Four weeks have passed since the start of the timber structure installation; one team is already beginning to install the second-floor beams while another team completes the first floor.
Just to give an idea of the installation speed of the system and the building’s dimensions:
1 month = 900 cubic meters of timber structures installed!









